Answer Posted / akash dubey
mainly m book is used to note the instruction given by
executive enginneer at the site, but any engineer whether JE
aur AE , there instruction can also be noted down in
measurement book
| Is This Answer Correct ? | 10 Yes | 21 No |
Post New Answer View All Answers
what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????
what is thumb rule for calculating the size of ISMB required for a particular length of span
what mean By core Billing
what is pile and deam foundation
what is the construction cost for per cft of multistorryed building in kolkata?
within an emergency scenario what are the safe systems of work a coss can setup as part of is duties
In csae of hume pipes NP stands for Non Pressure bur what does it really mean?
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
i have to give lap joint fo 1Mtr steel of dia12mm,whenever i did mistake i cut less 5cm plz tell me how much i will give lap joint so that length comes 1Mtr
What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.
A doubly reinforced concrete beam is 25 cm wide and 50cm deep to the centre of tension reinforcement. The centre of compression is steel is 5cm from the compression edge. The areas of the compression and the tension steel are 10.16cm2 and 12.56 cm2 if m=18 and the bending moment at the section is 7,000,000 N-cm. Calculate the stress in concrete and steel.
What does civil status mean?
What is the tensile strength of wood?
pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width
What is meant by cartesian coordinate system?