9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement
Answer Posted / bala
1. Consider 9.000m*9.000m*0.150m
Volume - 12.15Cu.m
* Cement - 41.31 Bags
* Sand - 6.075 Cu.m
* c.agg - 12.15 Cu.m
Is This Answer Correct ? | 4 Yes | 5 No |
Post New Answer View All Answers
TELL ME THE EQUATION FOR OGEE SPILLWAY
how much quantity of cement,sand and water required for 1 sq feet flooring work .
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
Define What is a kip?
why does the most of civil engg is not intersted to going for teaching field?
how to do sudoko puzaals?
How to hide dimensions in autocad?
What are the different types of runners?
in plate load test what is the thickness of plate 20mm 5mm 50mm none
Questions related to civil.engg in company
mix design procedure for 1:6 cement mortar
how can we calculate steel value, depending on load
why +1 to be followed for calculating the no of bars in BBS. Please explain
what is idealized curve for concrere and steel
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.