Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What are the dimensions of
1)Standard Brick
2)Nominal Brick
What is the difference between them in terms of use ?

Answer Posted / shafeekh pattambi

1)Standard Brick size =19x9x9cm
2)Nominal Brick size including mortar thickness =20x10x10cm

But the fact is that the size of the brick available in
market is equal to 20x10x7.5cm

Is This Answer Correct ?    18 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what are the layers of the national and heir aprox thickness??

2152


What are the composition of a landfill?

1256


what will happen if one could not properly follow the spacing of slab reinforcement bar?

2065


In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?

2522


what is the minimum cement content for M20 & M25 as per is code -456(2000).

3210


A super elevation of 60 cm has been provided on a 8m wide road and a curve of 260m radius .calculate the max.speed in km/hr of the vehicle that can be negotiated safely? Plz answer with full solution.thanx

1821


How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 600 microns?

6758


what is SDLC ?and write a 'c'program for to swapping the three numbers?

1869


How to find beam R/F cutting length

1840


Why Vitrified tile are getting pop up.

1049


If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.

2395


What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.

2104


How will you Engage Labours on Site?

1927


according to the painting co efficient, we should take the one side of doors (or) windows or both sides?

1788


Why are steel plates inserted inside bearings in elastomeric bearings?

1185