In third Party sale a sales order of 100 qty of an item
raised but vendor supplies 40 qty of that item. Now
business wants to close the sales order after delevering of
40 qty by the vendor. In this case what
should be done. please reply

Answer Posted / vikram

Rajiv,

What you are saying is called "trading process" where the
vendor delivers the goods to you and then you deliver it to
the customer. That is correct. In such cases, billing
relevance will be delivery related billing.

In the above case, it is stated that the vendor delivers
the quantity or 40 pcs. So in this case, the billing
relevance is "F" which is correct. Also this question is
very commonly asked in the interivews and they are looking
for "third party" related answers not individual purchase
orders.

So....I guess we both are correct!

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are some pricing routines and sd functional specs?

645


How can we set up to have the vat# be accepted in the ship-to master file data control screen?

597


Do you have schedule lines in the delivery?

636


What is Z transactions, and what is the use.Can u explain me what all we need to learn in logestic execution as SD consultant if we are showing shipment.

1339


In how many ways a sap system can interact with third party system. please provide the details to understand well about interfaces

1486






Hi, I have advance payment scenario where customer want advance payment cannot be used against another sales order and against any credit limit. Let me put one example. Customer X is having credit limit of 1000 USD, if my client is received customized product order then he will take advance for this special order but customer X is already enjoying credit limit of 1000 USD. In this scenario my client wants advance payment received cannot use against any sales order and against any credit limit. If I will post advance payment in F-29 then customer credit exposure will decrease against credit limit in FD32 which will affect normal sales order credit limit. Here customer does not want to utilize advance payment against credit limit of customer which is use for normal sales order. Please suggest

4009


Hi SD Gurus, Have you worked with an ABAPer for Smart Scripts / Smart Forms/ Form Lay outs used for Output Determination for your client’s requirement? Please provide detailed Explanation along with Configuration & Customization procedure, Steps, Analysis, path, t-codes and solution to the above questions as soon as possible? Also provide the logic for arriving at the resolution? If you can give simple example with simple coding written by ABAPer it would be great? Please include your real time data examples as many as possible with relation to your client/ Project? It’s Urgent!!!!!! I have interview within 1-2 days? So, I request you to provide solutions to above question as early as possible? Your timely help would be greatly appreciated? Thanks in advance Regards

1740


What is agenda of quick off meeting ?

637


The whse had to go to manual mode and we have been left with deliveries that were not created. Is VL10H the tcode I would use to upload data from an excel or text file to create the deliveries in mass? If so, what are the steps to follow? Thank you!

1592


What is rush order?

627


Who defines the account groups and give some tables in sap sd for customer master?

746


What is the relevance of tab 'Weight/ Volume Relevant' during Credit Memo Request and Debit Memo Request as it is being checked in both process at item level? As I know, it is relevant for re-determination of route at delivery level.

1613


In Third Party sale process, I am getting an error- in MIRO(Error No. M8889-A/c 893010 has been set as not relevant for Tax, but when I want to change the Account Assignment in ME21 it is taking only G/L A/C 893010 and refusing all other G/L A/C's by giving 2 errors. They are ME045-G/L A/c 39010 cannot be used(please correct)and ME038-No direct posting can be made to G/L A/C 34000. Experts please share your knowledge to solve this problem. Warm Regards.

3363


9. Any three major issues faced in the support project? what kind of issues they were

3879


Hi SD Gurus, I am applying for a position of SAP SD End user. In job description, they asked for Calender/Scheduling Experience. Could you please tell me about this Calender/Scheduling Experience in detail.Thanks in advance.

1586