how much quantity a carpenter do shuttering per day
Answer Posted / sachin
a carpenter can do 3 to 4 sq m shuttering per day
Is This Answer Correct ? | 253 Yes | 57 No |
Post New Answer View All Answers
how to calculate the crushing strength of cement concrete paver blocks 100x100x60 mm thich.
how to calculate the density for high density concrete ? or is it same as the density of RC?
Explain what is change order request?
How foundation is designed, Column design and beam design
How much quantity water should be placed in one cubic meter area?
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/
what is relation between SPT N value and driving piles after conducting a soil test?
Define What is rigging?
1.what type of the rock is most suitable for wet mix macadam in construction of road? 2.what is the highest maximum dry density and optimum moisture content can be acheive by using most suitable crush rock?
quantity of sand and cement for 10m2 plastering 10mm thick for the ratio of 1:4,1:3and its leabour data
Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot
material used for mendrel use to bend epoxy coated rebar
how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation
How to arrive d*d/162 , for finding the kg per meter , wt of steel