WHAT IS THE %WASTAGES OF CEMENT, BRICK,TILES, STEEL,IN 1
M3,10M2,1 TON RESPECTIVELY

Answer Posted / dushyant bansal

The Permissible wastage for cement is 3%, for bricks it is
2.5 % and for tiles it depends on the floor shape and size
which can be permitted upto 6%, while wastage is steel is
allowed only 2.5%

Is This Answer Correct ?    13 Yes 9 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

WHAT IS YOUR EXPECTED SALARY?

1610


How to calculate steel for beam slab and column

1355


use ofr concrete as per grade ?

1626


Kindly post me previous year interview questions with answer for post of Manager (civil engg.) for NTPC, IOC , GAIL etc. I have interview on july 2013.I will be very grateful to you. Please guide me.

1775


How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?

1688






what is the water-cement ratio of mix design while 30mpa in 7 days?

2614


which method is used in semi-rigid connection design??

1788


suppose that  156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.

2289


how much of the strength comes from post-production curing

1853


What are the benefits of rcc pipes over steel designed pipes?

766


I need model question papers for writing the Dubai municipality exam,for G+1

9329


What is the snap size in civil and how can we create it?

2294


where can i get the previous question papers for rrb section enginerr (civil)

1852


what is the water cement ratio? how to calculate it? list the wt. of constructions materials including concrete both ordinary and light wt. concrete

1860


Explain what is the difference between built area and super built up area?

670