How to calculate the no of bags required for 12mm thick 1:6
plastering?
Answer Posted / manish katiyari
finished volume=12mm = 0.012m =1.2m3
prop 1:6=1+6=7
cement req= 1.2/7
=0.17143
1cement bag=34.5 litres
=0.0345m3
cement bag req= 0.17143/0.0345
= 4.97 bags
approx = 5 bags
| Is This Answer Correct ? | 16 Yes | 20 No |
Post New Answer View All Answers
what is hydrostatic paradox?
I have completed building maintenance course in mcvc stream .. can I apply for the post of " sthapstya abhiyantriki sahayyak"?
1.what type of the rock is most suitable for wet mix macadam in construction of road? 2.what is the highest maximum dry density and optimum moisture content can be acheive by using most suitable crush rock?
How did the romans get water up hills using aqua ducts?
Wats the formula of eccentric footing and how was calculated from concrete qty
What is the maximum crushing load in Kg & crushing strength in N/mm2 for M25 & M 15 Grade concrete
115mm thickness brick work how to required mortar
why we are useing plastic under the lean concrete?and whts the advantage?
What is structural frames or systems?
what is the breaking strength of wall tiles
For submitting the project loan for bank Residential bldg,Suppose we take Provinding RCC mix 1:2:4 for footings No of footings,length ,Breadth,Height ,qty in cum, at last unit/Rate(Rs) ,i would like to know how do we get the unit/Rate
Describe the advantages and disadvantages of using plastic and timber fenders?
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
how to calculate reinforcment in staircase cranked beam?
which type of instrument included in plumbing work?name of instrument?