11 kv metering is done in my factory.Meter show PF 1.000
but kvarh lag&lead show 24&94 respectively & Avg.PF
is .956 .? is what i do for inproove my PF to 1.000
Answer Posted / vinit patil
Your Meter reads Power factor at load center. In your case
load center might be far away from your tariff meter. Since
your APFC meter shows PF 1.00 but at your tariff meter on
11 KV side p.f still lagging. This happens because of
transformer inductance. Add 10 % KVAR of transformer
capacity directly in ON position. Your problem will go out.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
what is the diference between the 4pole & 6pole DC Motors & what is advantage 6pole over the 4pole ?
i need to give section engineer (electrical engineer) for RRB. Please suggest some book
hi if anybody got model questions for cpcl Grade'A' electrical engineer position.send it to my mail please krishkumar22@gmail.com
what is the responsibility of C license holder in industry?
how is calculated the quantity of weight in hot test xlpe?
what is the eight bit unit?
hi frnds can any one help me ? plz send me placement paper of IOCL of Electrical streem .... plz send ....its urgent....
What products have you designed which have entered high volume production?
Who are the manufacturer for Nitrogen based Fire Protectio/explosion prevention for Oil Filled Transformers? India and international both?
How we can calculate the Amps for the cable Ex:- For 1sqmm wire how many amps we can draw (calculation)
if negative of DC supply used and positive is grounded through EGB, and if ELCB used in the system then is it sense the positive volatge and get tripped is it possible?
what is the pulse and audio frequency transformer? what is different between induction regulators and tap changing transformer?
what is PDU in transformer?? which company manufacture??
Q: How to calculate Transformer losses , tell us by Formula.
what will happen if OLR CT in all phases are short circuted