Answer Posted / cyber4india
The neutral should be solid and only Link should be provided
in neutral as if fuse is provided, in case of shock, it will
blow due to overload, but the supply will be available
through phase and the purpose of fuse is defeated.
In some case(domestic wiring) the neutral also contains
some potential due to unbalance of load in the supply (3
Phase). This holds true even if you are using the one out of
three phase . The neutral is displaced due to uneven
loading. Hence for any purpose of working, neutral Links
should also be disconnected along with the fuse in phase supply.
Is This Answer Correct ? | 2 Yes | 2 No |
Post New Answer View All Answers
How one can check the MAIN of a house wiring ?
How will be the single line diagram of series trip HT breaker? how it works?
What is the formula for calculating the Instantaneous Short Circuit & overcurrent for any breaker
power transmission pole used one support , that only for support or earthing
during installation time of transformer and alternator which points we have to observed?
1.WHAT IS A SMART CAPABLE DB ( DISTRIBUTION BOX) ? 2. HOW TO DECIDE THE TYPE OF DB TO BE USED ( RECESSED/ PLUG TYPE/ SMART ETC ETC? 3. WHAT IS MILLENEUM BUS BAR USED IN DB? 4.DIFFERENTIATE MCCB AND MCB.
how we can do the insulation on secondary of ct explain and so that tan delta will within limit
What shall be the secondary output voltage if the primary winding of a 220/6V, 50 Hz transformer is energized by an 110V, 60 Hz supply?
What is capacitance?
What OPGW is better than Microwave or PLCC???
what is the differencce inn series and cascade connection??
What is nichols chart?
Can XLPE/SWB/PVC (P3) 7C X 2.5mm2 be replaced by Can XLPE/SWB/PVC (P2) 7C X 2.5mm2??? P3 vs P2
Please clarify, 1. Is it required to lay two runs of GI wire along with Armoured LT cable if it is laid between one big mains (63Amps TPN SDF) to small main (32A TPN SDF) with proper glanding termination? 2. If the armoured cable with proper glanding is laid from DB to CNC machine, is it required to run two runs of body earthing to the Machine from DB? 3.If the armoured cable with proper glanding is laid from Substation to Hangar, distance is approx. 100 mtrs, is it required to do earthing at shop area though the primary termination at substation is earthed through gland.
what is feeder bay?