Answer Posted / anonymous
S.V = ((Actual Duration - Planned Duration)/Planned
Duration)*100
Actual Duration = Actual End Date - Planned Start Date
Planned Duration = Planned End Date - Planned Start Date
| Is This Answer Correct ? | 7 Yes | 13 No |
Post New Answer View All Answers
What is the responsibility of programmer’s vs QA?
What is the difference between three tier and two tier application?
aplitue questions will be based on wich type ?
What do we need to build a quality QC team ? a QC manager with all junior QCs or a QC manager with all senior QCs?
what is the difference between Desktop testing,Client/server testing and webapplication testing
How do u determine,what to be tested?
in the account there is 10,000 rupees and i entered 20000, in this case how will you test the application
You may be overqualified for this position we have to offer
Once automated, what are the types of functionality provides the highest Return On Investment (ROI) to the company?
What is an end-to-end testing?
what is the diff. bw separate database testers and manual testers with sql knowledge guys... iam confusing so much ,,in cmpny database testers are not working on manual..? both positions are same are not? explian clesly with example? thank u
Tell me about Agile scrum and what is your role in Scrum ?
What is the different between SIT and UIT?
Why you are selected software testing as career ?
What are the Major Functionality for a ATM machine ??