Answer Posted / samsirsameer
Bug Life Cycle:
Stage#1:
New: Test Engg finds a bug, drafts it and post in in Bug
Tracking system (BugZilla, PVCS, JEERA..ect)
Initially the bug is assigned to POC (testing) or TeamLoead
(development) or the test enggg directly assigns it to the
concerned developer (if he knows)
Stage#2:
i. Assigned: The Teamlead or POC or the tester himself (if
he is aware of teh developer working on that bug) assigns
the bug to the Concerned developer
OR
The POC or the development lead thinks that the posted bug
is NOT A BUG or NO PLAN TO FIX IN THIS RELEASE or
ENHANCEMENT (future request), he changes the status and
assigns the Bug back to the TEst Enginner. The TEst ENgg,
then closes the bug as per the lead/poc comments.
Stage#3:
The concerned Developer to whom the bug is assigned, will
look in to the isue
i.He may not be able to reproduce the bug. NOT ABLE TO
REPODUCE. He will assign it to the concerned test engg, the
test enginner willll verify and if repro he willl add his
comments (more detailed steps and assign) it to the
developer. If not reproduces, he will add conmmnents and
close it.
ii. Developer will fix and cnahe the status to
RESOLVED/FIXED and assigns it to Test Enginner
Stage#4:The test engg will reverify the bug in the fixed
build and if
it si fixed, he will add coments admn close it
if not fixed, he will add comments and assigns back to the
developer.
Again Stage#3 will come into picture and then Stage#4 until
the bug is verfied and closed.
Bug States:
New
Assigned
No plan to fix/Not a bug
Resolved/Fixed
NotFixed/Re-open
Fixed/Closed
Thanks, SamsirSameer
samsirsameer@gmail.com
Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
what is acid testing?
1.For a single module how many builds are possible 2.what will be the max or min time to finish up an single module
in an online banking software,users are connecting to bankserver by login.This login module can take below inputs for user. a/c number prefix-3 digits but doesnot start with 0&1 a/c number sufix-6 digits number password-5to 10 chars alphanumerics in lowercase areacode-3 digits number but optional purpose- cheque deposit money trasfer mini statement bills pay After filling above fields,user can click submit button to connect to bank server.prepare test scenarios for online banking s/w login.
Hello testers I am an Bsc Hotel mgmt Degree holders but now am doin my software testin programme, side by MCA Master degree an have 6 months exp i testing in company.. i want to change my CV according IT based. so can anyone help me with sendin any sample CV of urs.. do me this favour it wil be very helpful for me prepare CV for interviews....
what are the templates for daily,weekly and monthly reports? plz reply ASAP.
What does entry and exit criteria mean in a project?
hai friends can u expalin about real time process of testing at the company, like flow diagram
what is the difference between section & test feature in test case documention?
Can you explain the various elements of function points ftr, ilf, eif, ei, eo, eq, and gsc?
What is the responsibility of programmer’s vs QA?
Our software designers use UML for modeling applications. Based on their use cases, we would like to plan a test strategy. Do you agree with this approach or would this mean more effort for the testers.
Have you prepared traceability matrix and how to prepare it?
Tell me example for Risk,Mitigation,Assumption?
Iam new to testing field and i put lot of experiences so i want to get prepared for the interview in all the ways both in manual and Automation can any one help me how to answer there questions in real time. also can anyone send the top questions and answers to me plz its urget u can mail me at vaisu72@yahoo.com
*) Internal review defect gets detected… 1) During peer review. 2) By the own stuff member onsite/offshore. 3) During Informal review process. 4) None of these 5) All of these