How much does it cost for a R.C.C roof slab of size (25 X
20) given in feets using 1:2:4 concrete mix of M20?
Answer Posted / soumya
rate of M20 concrete per cum= Rs.2900
labour charge=250 rs
shuttering cost=300
total =2900+250+300=3450/cum
here area given as =25*0.3048*20*0.3048=46 sqm
assume roof thickness as 10 cm
there for Qty =46*0.10=4.6 cum
cost of rcc roof =4.6*3450=15870
Is This Answer Correct ? | 55 Yes | 29 No |
Post New Answer View All Answers
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
Explain what are the phases inspections are done by local authority while construction?
how we calculate the vol.of wet concrete..?
Journal entry Gross salary 10000 Tax 1000 Employee contribution 2000 Employer contribution 2000
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
Give me an example of a time when something you tried to accomplish and failed.
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing
how to find hardness of water?why it should be determined?
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
what is derating factor in cable? what does it mean if derating factor is high/low in terms of thermal resistivity of soil?
what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?
please briefly explain calculating or estimating steel quantity for a RCC column?
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
Explain the various stages of the project planning process in construction?