length of 4 core cable 95mm from substation LV VFD panel to
Motor at field approximately 150 meter. Motor stop and power
has been isolated from LV MCC ( Substation )to disconnect
Motor for services. After Motor completed service propose to
reinstall and reconnect Motor Cable, found earth cable
sparkling during touching at metal / motor body.
Inspect by clamp meter found earth cable have current flow
AC 1-2amps and all earth cable at MCC LV also have current
flow as same value. why it is happen?
Answer Posted / elavarasan.p
in sub station Hv side side leakage current will flow then
body earth will be samely to be connect to be in the lv
side some earth current will flow in lv side thats will be
approximately 1-2A will flow
| Is This Answer Correct ? | 2 Yes | 2 No |
Post New Answer View All Answers
How many size of cable required for a 300m long and 30kw inductive lode
Could the power factor on electrical system can affect the registration of the kwhr meter or the CT/PT?
Sir, I have applied for the of Jr.engineer(Electrical & Electronics) & ASST. LOCO PILOT at ALL RRB BOARDS. please send me all RRB Boards solved papers in the year of 2001 tO till date. i requested send me the papers to my id as soon as possible (jet_0991@yahoo.com). (This is very urgent) Thank You,
How to Preparation of online test
Explain what are inter-poles and why they are required in a dc machine.
How Diesel Generator start ?
Explain about Leakage Test.
working function importance of mdc meter
Should power factor be low or high?
Differentiate between digital phase converter and ordinary phase converter.
What is different bewteen low or high impedance busbar protection scheme
Which motor is 3.3 or 11kV more reliable, in terms of efficeancy,maintenance, reliability.
What are locations arc protection relay is fixed.
why we have to particulary use ACB for below ratings,even available of MCB,MCCB with that range ?
what is the saturation point of crgo lamination.