Answer Posted / girish pawar
The question is whats the Basics? and everybody saying about Basic data.
The basics of PP include:
1)Demand management- Planning strategies, PIR, CR .
2) MRP- technical processes of MRP as Net Requmt. Calculation ,Lot sizing , Scheduling , procurement types,then Evaluation of MRP
3)Basic Data management for Planning--- BOM, Routing , Workcenter , material master ..
4) Order management: Production Order, or Planned order, Process order, ot Run Schedule quantities in case of REM.
5) and the necessary activities as Goods Receipt, GI, n the ,backflush to maintain the lifecycle of Order.
Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
How is time management and payroll is integrated?
What are the types of master views for production and planning?
How the processing time is calculated in a wc when both labor, machine categories exist?
What are sequence, parallel, overlapping, splitting and where can we assign these
What is Inspection Points?
what are the problems you faced in MRP?
What is a ‘work center’ in pp?
Define stock requirement
In the monthly lot size proc, how to generate lot at the end of Period?
How did you configure the payscale structure?
Explain the mrp group and their uses.
What is detail scheduling
What do you do to run MRP for just one MRP Controller?
Control keys
What is Individual and collective requirements and differecne between them in MTO scenario?