ASAP is SAP’s solution to effective project implementation
and management.
It is divided into 5 major phases namely:
1. Project Preparation
2. Business Blueprint
3. Realization
4. Final Preparation
5. Go Live and Support
Project Preparation
1. Initial project Planning, scoping and goal setting
2. Implementation strategy
3. Team formation
4. Project Kickoff
5. Training
Business Blueprint
1. Refining goals and objectives
2. Requirement gathering
3. As-Is & To-Be documentation
4. Gaps Analysis
5. Documentation
Realization
1. Business Process Requirement implementation based on
defined blueprint
2. Baseline configuration and confirmation
3. Integration configuration
4. System management
5. Final configuration and confirmation
6. Development of program interfaces
Final Preparation
1. Unit testing
2. Integration Testing
3. User training
4. System management
5. Cutover
Go Live and Support
1. Migration to production environment
2. Support
3. Monitoring
4. Performance optimization
| Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
What is a company?
Copying is not possible. because an entry is missing in Table TVCPL: TA TAN Message No. VL473
In Intercompnay Billing scenario, Does Idocs get posted as we delivery is done from other plant and also the Intercompnay billing happens in the prcess. Though we have the same ERP system i.e. SAP only for all transactions.
Where and how is a 'business area assignment' done?
What is the latest release of sap transportation management? : transportation management
how to configure Supply chain management
What is handling unit in sap?
Explain about distribution channel?
Hi SD Experts, Have you created any Alternate Calculation Type (Alt Cal Ty) & Alternate Base Value (Alt Base Val) in Pricing? If so explain with an example? Explain in detail about the Procedure, Path, T-codes (if any), Logic, Analysis and finally resolution/ solution for calculating Alternate Calculation Type (Alt Cal Ty) & Alternate Base Value (Alt Base Val) in Pricing? I need your real time data examples more & more? Please do not give much importance to Theoretical definition concentrate more on Business Scenario & detailed procedure (Both Configuration & Customization) and Simple coding logic required if any from ABAPer from real time data? This question related to Pricing is most important as it is being asked more frequently in many Interviews? I have interview within 1-2 days? So, I request you to provide solutions to above question as early as possible? Your timely help would be greatly appreciated? Thanks in advance Regards
Hi Experts, Have you worked on IDOC’s? Can you list out important t-codes in IDOC’s and their brief explanation for what they are used for in general and specific t-codes which are useful for SAP SD Module? I have interview within 1-2 days? So, I request you to provide solutions to above question as early as possible? Your timely help would be greatly appreciated? Thanks in advance Regards
Name the necessary steps to setup a route?
What are the effects of posting goods issue? Explain.
Tell me a customization which you have done & worked for your client which is not in standard SAP settings? Explain the requirement along with detailed procedure & process,t- codes if any from your real time data in your project? This question is most frequently asked in many interviews.Please reply asap... Urgent!!!! Waiting for your response eagerly... Thanks in advance
Define whether the material can be used at which sales and distribution process
dear sd guru's..i am srikanth fico training fico..in sd-fi..i getting error's in outbound delivery ..vl248&vl461..i could not go for billing& icoming payment..i saw to solve those error message's from goolgle.but i could'nt solve...please give me solution in clearly...please sir's..!