how can calculate how much steam is to be required for
generation of 1MW electricty?
Answer Posted / chaitanya pithawa
no it is theoritical method,
but in real case, we should check the turbine by varying the
speed of the steam and angle of the nozzle,so 1 MW power is
to be generated,at that time we can check the steam velocity
and from that we can calculate the volume of the steam.
Is This Answer Correct ? | 9 Yes | 7 No |
Post New Answer View All Answers
Why should we hire you over the others waiting to be interviewed?
Give the safety precaution when working in a high place.
In order to derive the torsional formulas what are the assumptions taken?
In a rankine cycle if maximum steam pressure is increased keeping steam temperature and condenser pressure same, what will happen to dryness fraction of steam after expansion ?
Define the term latent heat.
Which case we will find maximum pressure and flow in centrifugal pump - circular casing or volute casing ?
How to recommend which type of coupling is suitable in particular area
In some engines glycerine is used in place of water for cooling of engine. Why ?
How can i Check at site this material is Powder coated CRCA ?
rrbchennaimodel question paper for current papers
Explain the advantages of cycloidal and involute gears?
What is the date, first titan launch from cape canaveral?
Hi! Greetings of the day. Can somebody tell me about as built duct sheet area calculation method. As we know that for this purpose A = (W+H)*2*L. But I have query about multiplication factors for elbows, tappers, offsets etc if there is any. Also refer the papers if available. Please revert. Thanks in advance.
Explain the difference between shear center flexural center of twist and elastic center?
Dear all, Will some one help me in this issue please? We are entering the Zero Stock Component in Maintenance Order, and we make a Check when the order creator is going to release system will appear Error, until he will not delete that zero stock components from the Maintenance order. but right now what the order creator is not releasing the order but he is going to save order, when's he save the order without release system will generate Reservation in the back ground, which should not happen for Zero Stock Components ? I need the way which we are doing in MB21, Reservation creation by thru Cost Center / WBS Element. At present if you run MB21 and you are going to issue the material system will not allow to generate the reservation if there are zero stock components in the list. please guide me for this issue ? Note : Simple what I need is I don't want to create any reservation thru maintenance order for the Zero Stock Components. Regards, Abdul Mujeeb