What is the step by step process in MRP

Answer Posted / kumar subhrata

There is different steps in MRP:
1. Activate MRP in your plant.
2. Create Master Data for MRP (Planning Calender, Quota Setting)
3. Create Material Master with Views like General data 1, Purchasing, MRP1, MRP2, Accounting1.
4. In MRP1 fill the following data (lot size - EX, Reorder Point, Safety stock, Planning Calender etc).
In MRP2 fill the following data (Plan delivery time) and after filling the other views save the materials master.
5. Go to Transaction Code MD03 to run thr MRP.
6. Go to Transaction Code MD04 to view the requirment.

Is This Answer Correct ?    30 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the essential components in sap mm?

803


What is the procedure to give specifications for developments?

638


What are the initial configuration steps for physical inventory?

628


What are ‘transaction keys’ while setting obyc?

708


What are some of the options available to transfer materials from one plant to another?

678






What is partner function & configuration

1144


What do you mean by consignment stock?

589


How did different versions of sap evolve?

668


What is the organizational structure in the materials management (mm) module?

646


What is an rfq and how it is different from a quotation?

658


If the recruiter is expecting thorough Knowledge\exp on the following topics:- o Material master o Vendor master o Purchasing o Release strategy o Inventory management What type of questions can i expect ? Please mention some important questions

1987


How is consignment material procured?

646


What is a 'stock type'?

650


What is an 'mrp area'?

701


What are purchasing information records?

632