What is the step by step process in MRP
Answer Posted / kumar subhrata
There is different steps in MRP:
1. Activate MRP in your plant.
2. Create Master Data for MRP (Planning Calender, Quota Setting)
3. Create Material Master with Views like General data 1, Purchasing, MRP1, MRP2, Accounting1.
4. In MRP1 fill the following data (lot size - EX, Reorder Point, Safety stock, Planning Calender etc).
In MRP2 fill the following data (Plan delivery time) and after filling the other views save the materials master.
5. Go to Transaction Code MD03 to run thr MRP.
6. Go to Transaction Code MD04 to view the requirment.
Is This Answer Correct ? | 30 Yes | 0 No |
Post New Answer View All Answers
What are the essential components in sap mm?
What is the procedure to give specifications for developments?
What are the initial configuration steps for physical inventory?
What are ‘transaction keys’ while setting obyc?
What are some of the options available to transfer materials from one plant to another?
What is partner function & configuration
What do you mean by consignment stock?
How did different versions of sap evolve?
What is the organizational structure in the materials management (mm) module?
What is an rfq and how it is different from a quotation?
If the recruiter is expecting thorough Knowledge\exp on the following topics:- o Material master o Vendor master o Purchasing o Release strategy o Inventory management What type of questions can i expect ? Please mention some important questions
How is consignment material procured?
What is a 'stock type'?
What is an 'mrp area'?
What are purchasing information records?