Can we connect two or more energy meters/Amp meters on one
CT set(Three phase).
Answer Posted / shariff
More 2 Ammeter/Energy meter can be connected on CT secondary,
provided their burden (VA) rating should be high, otherwise
its accuracy will fall.
| Is This Answer Correct ? | 22 Yes | 2 No |
Post New Answer View All Answers
What is the principal of motor?
what is meant by 3rd hormonics ?
How to minimize the eddy current losses?
Define de-sensitivity?
please send me latest & previous years question papers for IOCL Technical level questions
How to calculate Grid rotor resistance(GRR) losses in slip ring induction motor?
can anybody send the rrb chennai &rrb bopal question papers of 2006&2007.My exam is on 12 oct 2008.Its urgent
how we calculate the withstansing current capacity of wires&cables?
State and define norton’s theorem?
what about electrical pannel.? What is meant by plc pannel.?
two way ckt diagram can be drawn by how many ways? give diagram
what happen if the supply is given to the stator of the 3phase induction motor with out assembling the rotor ?
why need to be maintain power factor for industrial customer?
If I have Energy Meter Ratio as 100:5 & Also I have CT Ratio as 50:5 then what will be my multiplying Factor(M.F.)
What will be the effect if I use inverter as UPS mood?