in pile foundation pile socketing length depend on which
factores?
Answer Posted / prasadarao
generally socketing is boring further after the strata ia
hard rock generally socketing is done twice the diameter of pile
| Is This Answer Correct ? | 5 Yes | 1 No |
Post New Answer View All Answers
Why M15 is replaced by M20 when ammendment are made in IS456 in 2000?
for pretensioning which will yield first and same for post tensioning?
What is Base Shear ?
Why should you consider yourself fit to be hired by jindal steel.
Why are separation membranes used between concrete pavement slab and sub-base?
How can you distinguish between sorption, absorption and adsorption?
why is M30 grade Concrete use for Foothing & Column M50
What is M40 _ TOR - EQ and B.F.S
In few lines, please be elaborative on extras and talents that make you a potential candidate for the post:
Explain how you can use different dimension tools in CAD? What are the different dimensions available?
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
important question on stones
what is castigliano theaorem
Exterior Joints,define
For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)