Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

On what basis no of earth pits are to be decided either for
transformers or for equipment?

Answer Posted / mrudang

earth pit is depnd upon

on vector group of transformer which we are used
equipment body earthing ,in delta connection we required
earthing transformer to protect from earthfault current

Is This Answer Correct ?    1 Yes 7 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how to put cable sizing and cable glands size for respective cable & Cable Lug size in a DB sectors???

2159


Is it possible to make a 5P10/ CT Ratio 50/1A Burden 5VA

1713


is it possible to turn on the single phase star delta on delay timer using 24 v dc ?

2029


HOW DO YOU CAN CHECK A 15KV DIODE, WHETHER IT IS OK OR NOT?

2035


how can get electrical c licence.now i am working in spining mill , transformer capacity 2750KVA. SANCTION DEMAND 2250KVA. PLEASE ADVISE ME . MY CONTACT NO 09944226823

1796


what kind of technical test that i need to learn because i have an interview tomorrow.. please someone help me..

2015


Thermal withstand capability under full short circuit conditions, in terms of number of times of occurrence of short circuit and corresponding anticipated percentage reduction in transformer life.

2428


I have 2500KVA transformer delta/star,13.8KV/380V provided with LV 4000A breaker. Already I have 2300KW motor feeder with a full load 90%. Is it possible to connect another 1600A from that breaker? If so how the calculation is done?

3805


in india per day how much power is generated including all power station

1938


what happen ehen synchronisation is done at below rated speed

2137


Is a contactor (or master relay) required between incoming lines and a VFD? The question goes to safety. If a contactor were used before the VFD and an e-stop engaged then the motor will coast to a stop (i.e. VFD loses power) instead of stopping much faster if the VFD braking fucntion were used. It would make more sense to keep power on the VFD.

2174


Give idea about General Engineering. From which book i can study this topic. Pl. reply me via email. My email is ravi@bhelhwr.co.in, also give the name of book/website, from where i can prepare it.

2049


i need some project topics along with circuit diagram in the electrical adnd electronics engg and also give ome website regarding projects.my mail id is thenmozhi2k7@gmail.com .please help me.

1951


role of europe union in UK safety legistlation (electrical safety)

1760


What are the parameters of water ( Water quality )to be monitored in Centralised HVAC ( water cooler chillers )

2060