TO operate transformers in parallel, vector symbol of the
both should be same.If one transformer name plate is not
there, how can we conclude that whether the transformer is
having the same vector symbol or not?
Answer Posted / mgalalkhedr
This vector group test is done at site to check if their is
any damage in the windings during transportation and
erection.
3 -phase AC supply is given on HV side. R-Phase HV and r-
phase LV shorted.
Then to qualify the test following conditions are to be
satisfied after measurement of voltages.
nR+nY=RY, By>> Bb and Yb=Yy.
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how we can explain arc heatng?
what is the Connected Load (kW) or Contract Demand (kVA)of mahindra nasik plant??
briefly explain the main blocks found in a microprocessor based system
How to calculate the fuse rating depend upon the DC circuit?
Motor,transformers,capacitor tubelight etc....
1.What will be stored in online ups EPROM IC?
What is tranformer differtial?
What is the formula to calculate distribution transformer De-rating on iron losses basis
5.WHICH TYPE WELDING PROCESSES USES NON CONSUMABLE ELECTRODE.........
explain the mode of metal iranafer in Co,welding
How 48-relay (incomplete sequence) functions?
1.Z transform always lies around ? a) origin b) pole c) zero d) z=1. Multiples Mcqs which is bother me can’t find answers on internet. Some help required with little explanation . Note: this is not homework or related to any test. Thanks
What is the necessary and sufficient condition for stability.
what are all the components required to assemble solar panel other than pv cell?
What happens if we give the supply to the rotor of induction motor and make its terminal shorted?