how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?

Answer Posted / sateesh patil

If you Consider M25 Grade Concrete Nominal mix Design is
1:1:2(1 Cement:1 Sand:2 Aggregates)

1+1+2=5

Volume of Dry Mix=1.5% X Volume of wet mix
If you Consider 1 Cum Concrete
Cement=1/5X1.5(1)=0.3 Cum(1 Bag of Cement=50 Kgs=1.235
Cft=0.035 Cum)
Then 0.3 /0.035=8.57 bags=428 kgs

Sand=1/5X1.5(1)=0.3 Cum=10.584 Cft

Aggregates=2/5X1.5(1)=06 Cum=21.168 Cft

Is This Answer Correct ?    53 Yes 172 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft

1734


HDPE pipe standard bends using for TSE irrigation? is it possible to use 30 degree?

1740


how many spacers we need for 1 ton reinforcement? aprox.

4923


What are the different approaches in designing the floors of the service reservoirs?

767


column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial

3496






What is the difference between a wood shake and wood shingles?

704


how much cement sand n bricks required in im3?and how much in plaster?

2113


Explain soil analysis?

669


Define aligned dimension?

672


What is the difference between one-way slab and two-way slab?

668


How many bricks are there in 100cft?

847


at which depth the construction of tunnel is economical from cost and engineering aspect.

1316


what is the water cement ratio of 1:6 and 1:4 cement sand mortar. reply soon

2346


How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?

2055


how to calculate number of bitumen for road asphalt

974