Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Why 50hz and 60hz frequencies are used by the world, why
they are not taking 55hz?

Answer Posted / saa

RPM of Prime mover is related with Electrical frequency.

Some countries use 50 HZ with 1500 Rpm for 4 pole
Some countries use 60 Hz with 1800 Rpm for 4 pole

for 55 Hz 4 pole RPM of Prime mover will be 1650



Some countries use 50 HZ with 1000 Rpm for 6 pole
Some countries use 60 Hz with 1200 Rpm for 6 pole

for 55 Hz 6 pole RPM of Prime mover will be 1100


Itz just matter of Choice.

Is This Answer Correct ?    22 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to calculate or formula to calculate rhe power in 2 phase system ??

1490


Please clarify, 1. Is it required to lay two runs of GI wire along with Armoured LT cable if it is laid between one big mains (63Amps TPN SDF) to small main (32A TPN SDF) with proper glanding termination? 2. If the armoured cable with proper glanding is laid from DB to CNC machine, is it required to run two runs of body earthing to the Machine from DB? 3.If the armoured cable with proper glanding is laid from Substation to Hangar, distance is approx. 100 mtrs, is it required to do earthing at shop area though the primary termination at substation is earthed through gland.

2020


what is the reason for indication of light in the earth lamps of main switchboard.if there is an earth why does one lamp get dim and the other two bright.

2337


What is Auto Mains Failure Panel & Auto Synchronizing Panel

1926


From past few months I am getting lagging pf even though sufficient capacitors used in circuit. Where is the problem pls answer

1415


why do you add the load short circuit impedance when considering short circuit amperage. It seems that you should only consider supply. If you need to consider loads and you don't know what loads are to be added , what would be a good sub-transient reactance rating for the loads?

1786


What is the meaning of utility ground and clean ground? How the distribution panel is grounded?

2529


how to size H.T & L.T Panel ?

2114


what is the circulate the diesel in DG in side pls tell parts name and picture with circulate the diesel

1979


Explain the fundamental difference between emf (electro motive force) and pd (potential difference) ?

1124


i am completed my degree(B.E EEE) 2014 anychance to get electrical licence plz help me

2135


How does zener phenomenon differ from avalanche breakdown?

1152


what is the function of bearing in dc mchine" and where it is placed

2575


I am going to appear for the RRB Chennai Section Engineer online exam. Please send me the question papers from 2001 to date to my mail id:upendrakrishna20@gmail.com,plz send me ,or send any other rrb papers plzzzzzzzzzzzzzzzzzz

2074