IN CIVIL ENGINEERING DESIGN WHY WE ARE USING LIMIT STATE
METHOD IS BEST?
I THINK WORKING STRESS METHOD IS BEST?
EX; FOR COLOUMN DESIGN IN LIMIT STATE METHOD AST
IS;1913SQ.MM
SAME TIME WORKING STRESS METHOD IS ;2213.
SO I THINK WORKING STRESS METHOD IS VERY STRONG COMPARE
THEN LIMIT STATE METHOD?
MY OPENING IS CORRECT OR NOT? PLS TO EXPLAIN SIRS
Answer Posted / rupesh belsare
in limit state method we are considering facorad load that
is in this method their is more factored of sefty than
workingstress mathod and one more reasone is that in limmt
state all kinds of limit is consider while designing e.g
limit state og bending, which is not considered in working
stress method
| Is This Answer Correct ? | 14 Yes | 0 No |
Post New Answer View All Answers
a butt weld is specified by
dialation means
Did any of the egyptian pyramids ever fall down?
What is the use of mirror command?
1.Why we are preferring 43 grade cement than 53 grade cement. 2. Approximate cost difference between 43 and 53 grade cement. Thanks.
How we can calculate the cement, sand,bricks , water , quintity in 1:6 Ratio 1 cubic metre b/w and 1:4 Ratio in 1 Squre metre b/w????
construction workers how much time take one work or qty
I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.
How does siphoning work?
What is the release of lien?
Why are steel plates inserted inside bearings in elastomeric bearing?
how to calculate spacing rod in column
What is M40 _ TOR - EQ and B.F.S
How much quantity of rod binding work by a rod binder per day
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?