WHERE to use CVT & PT.

Answer Posted / jagan

it is connected bet communication wavedrop and Ct.it is
used for met &pro..it is nothing but acapacitor arrangement
due to this large level of voltage will be stored and due
to small stepdown transfomer inside it is reduced to as
plant req.Ex;400kv/1.732/1.1kv/1.732.

Is This Answer Correct ?    4 Yes 6 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to Preparation of online test

1071


What happens if we run alternator on under frequency? 

1632


what is the calculation involved to design the heater to heat 10KL of water in temperature control unit?

1473


In CTs tan delta point should be earthed , what is the reason behind it?

2496


what is auto re-closer?

1987






when ID fan will immediately stop through VFD what exactly cause and problem the ID fan

983


can any one tell in easy method for circulating current ??

1639


What are the two basic types of transformers?

616


Please brief what is sinewave

1723


What is Traction? 1KVA Alternator, How much urrent taken?

1595


Is it possible to measure correct value of earth resistance & cable insulation ristance with out disconncting earth lead & both sides of cable ends? If not, any other method to measure ER & CIR with out disconneting from the system.

1647


sir,in our plant we r using SATEC PM172E power reading meeters in HT panel side it is monitoring the MB data smart viewer(sever).but last one week we did not get readings inthe server only available in meeter.tell me how communicate meter and server. and also what steps we take for checking.

1779


if an insulated power and control cables of a running gas diesel gensets laid direct in an open trench i.e, trench bed is not rcc of a power house in which rain water, spillage water alwas exists and all power control cables remains submerged even when gas gensets of 480 kw each runningin on load. These power &control cables runs from power house to switchgear room through these trenches in which water remains most of the time. pl explain its merit & de-merit

1401


what is the minimum pay scale for electrical engineer (building construction)in kuwait? plz revert back with yrs of experience & pay scale respectively.

1680


As per standard, transformer body earthing and other Equipment earthing (Equipment earthing) did not connect. but in LT side termination we are doing metal glanding in both side Transformer to PCC Panel through armoured cable, now X'mer body earthing and PCC Pane earthing (Equipment earthing) both are connect.is this safe for X'mer or other equipment?

1186