Do you have different BOMs for a material in different plants?
Answer Posted / jinchandramule
Yes,
we can have more than one BOM FOR A MATERIAL in Different
plants.
Depending on the plants reqts and the components
requirements,as well as the alternative requirements .
| Is This Answer Correct ? | 15 Yes | 1 No |
Post New Answer View All Answers
Explain service level agreements
What is the uses of production scheduling profile and what the configure have you done current project
What do you mean by basic dates
Mention what is the t-code for changing production order and to display production order?
define variable cost
What is mrp controller means?
Explain the lsmw and the steps involved in them.
Are there any reports in sap to list of material requirement from ltp ?
I have having 14 years manufacturing experence & 6 years in SAP-PP/QM.Was a core member during implementation.Now I want to work as Functional Consultant in SAP-PP/QM.What should I do for getting the jobs.
What is Material status and which view of the material master it is available?
What is phantom item & sub contracting
What is the Difference between TECO and CLSD?
What is the planning time fence?
Difference between Routing, Ref op set, Rate routing and Ref rate routing.
What are sequence, parallel, overlapping, splitting and where can we assign these