in our sub station why we step down firstly 33kv\11kv then
11kv to 430v. can we direct step down 33v to 430.v.
Answer Posted / cv raman
Genarally load centers are very away from the Generating
stations & scattered too.No of 11/.430KV SS are very high
compared to 33/11KV SS. In the view of construction cost of
the 33/11KV SS is high compared to the 11/.430KV SS. At
this condition , construction cost of 33/0.420KV is very
high compared to the cost of 33/11KV SS. If we propose
33/0.420KV SS in all load centers the no. of ss will become
very high and construction cost will be very high.
Technically we can go for strigh step doun but it is not
economical.
| Is This Answer Correct ? | 16 Yes | 4 No |
Post New Answer View All Answers
Comment on the working principle of operation of a single-phase transformer.
If Polarization index of motor 8.75 at 500volts of medium voltage 4.16 KV motor what this mean winding good or bad pl answer if any reffrence book give me the link
What is the end effect of linear induction motor ??
What do you mean by distribution transformers?
what is the sludge current
how is the connection of a 3 phase ct trivector meter done on a pole mounted transformer
10 Mtr Hight of Lighting Arrestar how much area coverd??
if a.c supply is given to the motor,, what happen?
please forward me the type of questions which would rise while me attending to 33KV Electrical License to my mail ID:vadrevu_raghava@yahoo.co.in
What is the HVDC Transmission System? What are the conditions applicable to lay an HVDC Line?
what is residuel magnetism. and how order lead acid batteries for 24 volt. emergency lighting system.
Define piezo-electric effect?
how to electrically make connection to ferroli GN2N?
Dear sir, In our plant have Station Transformer having capacity,i want to know, why LV side 40 - 40MVA is given? & how we can get 6.3 KV supply from tertiary(i.e. Open delta connection), Vector Group YNyn0 - yn0 +d MVA Rating 80MVA / 40 - 40MVA + 26.7MVA Voltage rating 420 (Tap range +6,to -10)81.25% /11.5KV - 11.5KV +6.3KV
all interview questions with answers of ntpc (2000-2009