deference between DCS and PLC including date processing and
architacture.
Answer Posted / parmar.ic@gmail,com
1) PLC=Programmable Logic Controller DCS=Distributed
Control System
2) PLCs are stand alone and perform a particular task,
DSC is a network of PLCs/RTUs that communicate in some
fashion to accomplish a particular task.
3)PLC only handled sequential process than DCS can handled
both Continue process and large loop control.
4)PLC doesn't have dongle so peple can crack the software
easy.
DCS have a dongle so it's only license to industry which
have it.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
why we use cascade control and feed forward control in 3 element drum level control measurement of steam drum .what is cascade and feed forward control system ?give example .
what can of fault ofently come in vibration mesurement?
How d.p. Transmitter can be applied to open tank?
How many are the types of instrument cables in terms of No. of pair.
what is the field bus calble ? what are diffrences in orang colur cable and black coular calble ?
Q- What are the application in which PNP transistor is preferred over NPN ?
What is the difference between modbus,fieldbus & profibus
how many pulses are required by a ac induction servo motor of 4 poles with 50 Hz frequency to rotate by 1 degree?
describe flow nozzel principle?
can any one explain in which term we are flow flow is it volumetric r is it mass? and y
how to do dynolab wind speed sensor loop test, how to simulate value,i have simulate mA 4-20mA but not responding in DCS faceplate, please kindly advice me any one.
Explain the use of hair spring in the pressure gauge.
Give Detail information about plc,dcs,and scada system?
What is standard procedure of manual mapping in Radar type level transmitter?
what are the different types of Protocols? & their applications.