during parallel operation of two ac generator which
condition must match before taking both parallel i.e
speed /voltage rating /kva/exciation
Answer Posted / kamlesh g patel
incoming machine voltage should match the system/other
generator voltage.
frequency must be the same.
phase sequence must be the same.
| Is This Answer Correct ? | 12 Yes | 4 No |
Post New Answer View All Answers
Why back emf used for a dc motor? Highlight its significance.
hwat type of motor is used in thermal gas turbine hydro nuclear power plants and why
What are your future plans for the company if permanently employed?
hi friends how 3 phase converter functioning ?what is working principle of rotory phase converter ?
how to calculate the Neutral transformer impedance?
1hp= how much rpm
What is an Air COmpressor
what is the meaning of the symbol << >> put in transformer drawing
how we test a 3 phase motor on single phase supply....? HOW WE RUN A 3 PHASE MOTOR ON SNIGLE PHASE. supply for testing..? how we verify of a 3 phase motors 6 wire & name thame a1/a2/a3..b1/b2/b3 and c1/c2/c3 for connecting star delta starter ........i have only 1 phase supply ? help forum..........
what is the basic need of domestic loads 1- voltage 2- current
On what basis the the size of Lightning arrester for buildings are selected ?
what is difference between bus coupler and auto transfer switch
How to select a contactor? How many types of contactors are available
how to Select its CORE in electrical cables based on its applications? or Application of various types of electrical cable based on it CORE?
What are conduct on the testing in cf in ur site?