during parallel operation of two ac generator which
condition must match before taking both parallel i.e
speed /voltage rating /kva/exciation
Answer Posted / pswin
Parallel operation of alternators is called synchronization. A synchroscope is an instrument for indicating the correct time for switching on. Three conditions must be fulfilled for synchronization.
1. Voltage must be same.
2.frequency must be same. And
3.voltage should be in phase position with respect to local series circuit.
Additional requirement is that the phase rotation must be the same.
| Is This Answer Correct ? | 27 Yes | 3 No |
Post New Answer View All Answers
1.what is the reason for transformer and lightning arrester blast in 33kv system
What is the difference between voltages or potential difference? And what are they?
what is the function of gss in the dg set.
what is the standard values(Megger test) of resistances between L&N,L&E and N&E for a system on IEE regulations?
I want formula to calculate cable size as per load given in length & amp. I searched many sites but didn't right answer. Please reply me asap.
What is the use of iron core in a transformer?
Write the programming software name for LG, SIEMENS,Messung,AB
I WANT TO know WHICH WAY IS BETTER FOR CONNECTION BETWEEN POWER TRANSFORMER AND MAIN DISTRIBUTION PANEL. 1-IS BETTER WE USE CABLE? 2-IS BETTER WE USE BUS DUCT? my transformer rate power is 2500KVA
define hysteresis loss, eddy current loss and windage loss
Who are the manufactures those manufacturing 3Cx2.5sqmm FRLS cables. I heard about FRLS technology adopted only in wires useful for wirings
The series field winding has low resistance while the shunt field winding has high resistance. Why?
Dear all i want to know SEWA Electrical Supervisor Licence test Previous Year Questions ? If any body know please send to me zohairaukllah@yahoo.com
What is cross over distortion? How it can be eliminated?
what are the different sizes of U.G. cable & where these cabl;es are used according to voltage ..
please write motor, transformer, Generator setting, fault level calculation of Tr.etc