Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?

Answer Posted / sjtbehera

In the case M30 concrete we calculating by design mix.but
incase of norminal mix we can use 1:1:2.
calculating cement, sand and concrete.
toal ratio=1+1+2=4
cement = 15.4/4=3.85cum=11bags
sand=3.85*1=3.85 cum
chips=3.85*2=7.7 cum

Notes: why we divided 15.4
but it is difficult to acess exactly the amount of each
material recquired to produce 1cum.of wet concrete when
deposite in place.
to find out volumes of cement sand & coarse aggregate
divided a numerical no. 15.4 variable up to 15.7 according
to proportioning and water cement ratio by the summation of
the proporation of the ingrediants used and then multiply
the result thus obtained their respective srength of
proportion.

Is This Answer Correct ?    156 Yes 216 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)

2387


residential projects,structural.

2818


 rcc floor to floor  4m. in column reinforcement where we provide lap in exact location.     

2019


For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?

1749


What are moment of inertia and its importance in civil engineering?

1216


how we can find sieve #4 is 4.75mm?

2281


TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING

2464


types of survey and levelling instrument ?

1798


does a b.tech civil engineer fresher supposed to know how to design rcc structure?

3401


What do you mean by tolerance factor of concrete ?

3092


How much quantity of rod binding work by a rod binder per day

1441


How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?

2216


Explain moment of inertia?

1060


for a column of size 400*230mm column reinforcement= 8-20x(cant write the symbol,i hope u guys undersstand,something like (fi) column stirups=8x@(4l) 230c/c 1)what does these mean 2)how to calculate quantity of steel for this column(ceiling height 11 ft)

2130


if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.

2072