Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to Calculate steel

Answer Posted / arun parashar

Steel can be calculated by kg or tonnes.
STEEL WEIGHT CAN BE calculated BY THE FORMULA OF
= D*D/162
D :- Daimeter of steel bar

Is This Answer Correct ?    125 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain what is the release of lien?

1237


Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish

2644


Exterior Joints,define

1939


How high should the water tank be to provide a 60 psi at base of this water tower?

1144


How do you maintain water pressure?

1198


how to calculate the steel in 500yard

2522


how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing

2323


What quantity of 1.0 m3 bricks required?

1144


Difference between pre-tensioning and post-tensioning.

1181


in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?

2312


If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?

1835


strength of bitumen concrete with 80-100 & 60-70 grade bitumen

2122


Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required

2031


There are two buildings one taller and one shorter whose time period will be grater and similarly the frequency ?

1668


how many digree of freedom in four bar chain

2407