in our sub station why we step down firstly 33kv\11kv then
11kv to 430v. can we direct step down 33v to 430.v.
Answer Posted / devesh mishra
yes we can directly step down from 33/.433kv.
the lv side remains constant for 11 or 33kv & hv side
depends on load i.e,
for load upto 1.5 mva 11kv ht line is required,whereas
for load above 1.5 mva 33kv ht line is required
| Is This Answer Correct ? | 3 Yes | 12 No |
Post New Answer View All Answers
how to determine motor size for a fan application?
In EHV transmission line a neutral grounding reactor is often placed at neutral point of shunt reactors. What is the recommended protection for this neutral grounding reactor? Should I use a fast closing switch to bypass neutral grounding reactor when this protection operates?
how to calculate insulation level of transformer?
how freewheeling diode improves the powerfactor
hi, could someone help me to find a control design for syncronising panel .
What is servo motor and what are the applications of servo motor?
Importance of fault current in power transformers and how to monitor the same? How is it different from winding temperature?
How can I calculate ISF of current transformer?
hi can any body send me syllabus of rrb electrical section engg... and past pepar also of any board...
how is the magnetic current test is different in delta-star and delta delta transformer.
Why do we need interlocking in a HT metering or Ring main unit switchgear?
1.What will be stored in online ups EPROM IC?
for compensate 315mh inductance ,how many capaciance required?
How many energy meters can be connected on a 15VA Voltage transformer. please send a calculation sheet.
what is the working process of over & under voltage relay.