1) MPS is maily focused for critical or Top level items
(single level of BOM), where MRP is used for bottom level
(All level of BOM's- Like single item Multilevel, Single
item Single Level)items.
2)Compare with MRP, MPS is a long term Planning.
3) Example for MPS is Television Manufacturig Industries,
Example for MRP is Garment Manufacturing, Sugar Industries.
Note:
For both we need to maintain the safety stock.
| Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
What is the difference between “planned consumption” and “unplanned consumption”? Can safety stock calculation be done on either of these?
what are the settings needed for variant configuration?
How to create object dependencies in a bom for a configurable material?
What is meant by payscale structure? How did you configure the payscale structure?
Explain how the pp module is organized in sap?
What is the use of infogroups?
What is "work center" in sap pp and what is the use of data in work centers?
Explain the mrp group and their uses.
What are the types of MIC?
How is the processing time calculated in a wc when both labor, machine categories exist?
How do you restrict the data to be entered in the payroll area?
What is golive actually? What is the role of a functional consultant in golive actually?
What is sla (service level agreements)?
Explain what is the need of mrp list if the stock requirement list is already given?
Can't one material be assigned to more than one operation in a routing?