How much quantity of Cement and Sand required for Cement
Sand Ratio of 1:1 and volume of pile is 0.61 m3
Answer Posted / s.r.shiradhonkar
vol of pile is 0.63 cum
Material required
Metal (0.80 cum/cum of concrete)i.e 0.8*0.61=0.488 cum
Sand (0.40 cum/cum of concrete) i.e 0.4*0.61=0.244 cum
cement(0.40 cum/ per cum), (as cement sand ration mentioned
1:1). cement required= 0.4*.0.61=.244 cum. 1bag of 50 kg
have volume 0.035 cum. there for bags required=0.244/.035=
7 bags.
S.R. Shiradhonkar
Amarawati.
| Is This Answer Correct ? | 6 Yes | 7 No |
Post New Answer View All Answers
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
A super elevation of 60 cm has been provided on a 8m wide road and a curve of 260m radius .calculate the max.speed in km/hr of the vehicle that can be negotiated safely? Plz answer with full solution.thanx
For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.
What is change order request?
What are the composition of a landfill?
Define What is the tallest man made structure in the world?
what is tension footing?
how much used soil in 1 brick of standard size?
Explain the different types of building contracts?
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
Rate analysis of Vitrified tile in cement mortor 1:3
What is meant by Crystal Concrete?
At what point does a circle start losing area when being flattened?
What is the difference between pvc,cpvc and upvc and where it is used as per their properties?????
Which percentage of carpet area use in plot area of office building.