Answer Posted / nicola k
In SAP most cost objects - other than cost centers - must be
"settled" at period end. By means of the settlement the
costs incurred for the cost object (project, internal order,
...) are debited to other cost objects and/or G/L accounts.
The settlement rule, a table maintained in the cost object
master data, describes to SAP how the costs will be settled:
receivers, percentages, full/partial, etc..
Cost are settled when the user starts the settlement
procedure at period end.
Is This Answer Correct ? | 54 Yes | 5 No |
Post New Answer View All Answers
How is the budget for the project controlled?
Define project definition?
Where do we define time profiles? What is evaluation period?
Do you think professionalism and integrity are essential qualities of a pm?
How does coding mask affect the project? Tell the menu path for the location where it is created.
Can revenues be linked with activities?
Explain value categories
What are some techniques used for defining scope?
What do ntw mean?
What are processes and process groups?
what do activities mean?
What do you understand by plan baselines?
You want to set the options for capacity report cm01. How would you do that?
explain relationship
How should changes controlled?