Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to calculate optimum loading for transformer?

Answer Posted / khalid hussain shaikh

POWER=1.732*VOLTAGE*CURRENT*POWER FACTOR
HERE POWER=2500KVA
VOLTAGE=11 KV
POWER FACOR AS STANDARD=0.85
I=?
I=2500KVA/1.732*11KV*0.85
KV CANCELLED EACH DENOMINATOR AND NUMARATOR,
I=2500/1.732*11*0.85
I=154 AMP (11 KV SIDE)
I=2500 KVA/1.732*415 V*0.85
V CANCELLED EACH DENOMINATOR AND NUMARATOR
I=2500 K/610.963
I=4.091 KA
I=4091 AMP

Is This Answer Correct ?    10 Yes 16 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how solar power plant energy meter multiplication factor

2032


checking procedure of capacitor based motors.used in fans etc?

2057


how to select proper cable for ct wiring so that drop within the limit.

1919


Define steady state error.

1023


what are pilot cells

2011


Dear sir, By which formula u can calculate for a particular kv line there is a range of mw.

2059


whate is the meaning of balance/unbalance,in stabilizers type

2089


What is the relation between frequency and motor rpm?

1799


explain the mode of metal iranafer in Co,welding

1521


what is size of 3phase 4wire cable to be used for 11 ton ductable A.C and how to calculate cable size for different load

3968


What is the main use of rotary phase converter ?

1088


what is proper capacitor placement? How to evaluate capacitor size?

2064


what is meant by LCR meter? where its useful ?

2000


1) What are your personal strength? 2) What are your personal areas of improvement? 3) What are your expectations from from a particular job? 4) what are your carrier objectives?

2459


what is the min and max ohmic resistance for the earthing rod installed for lighting poles for street light network

3684