how we can select MCB ratings according to Voltages, Curves.
Answer Posted / balakrishnan
1.We can select the MCB's acoording to Voltage is simple,if
we want 230V,select single pole MCb's else want 415V select
3 pole MCB's.
2.We can select the MCB's according to to Curves is also
simple,there are several types of curvature available..
there are,
B type: react quickly overload i.e 3-4.5 times of full load
current
Type C: react more slowly,these are recommended for
inductive with high inrush currents like fluorescent lamp.5-
10 times of Ifl
Type D: 10-20times of Ifl,recommended for very high inrush
current.
Type K: 8-12 times of full load I,recommended for cable
protection to be provided which include
motors,capacitors,and transformers
Type S: 13-17 times of Ifl,recommended for protection of
control Transformer,
Type Z:
| Is This Answer Correct ? | 31 Yes | 2 No |
Post New Answer View All Answers
why does make gain margin and phase margin on same plot.?
What are operating procudures & Safety precautions to be observed while operating OLTC in manual mode ?
How much load can take a 16 mm aluminum cable 3 phase
what are all types of cross section in AC cables?
what is mean by kneepoint voltage? when it will happen? ( my doubt is, if CT secondary is open means ct get saturation or blas? what are factors are required for calculations? plz give currect anws:
pre arcing time of ehv breaker
what is acceptance test in electrical engineering.
HOW TO CALCULATE HV TEST VOLTAGE FOR ELECTRICAL EQPT.
how to calculate current carring capacity of cable and cable selection? 1) copper flexible cable 2) copper armoured cable 3) Aluminium cable
Control wiring of a dol starter for forward and backward
What was your role in the silicon evaluation/product ramp? What tools did you use?
What are the advantages of a three-phase system over a single-phase system?
We have received supplies of the ordered material. payments against the supplies also released. Where ST paid 4% against form C. Meanwhile it has been observed that 25% of material supplied was defective. Please suggest whether the issuance of C form from our side would be stopped till settlement of liabilities.
How to test REF relay testing for LV panel as per Kahramaa standard?
Is it required to lay GI wires along with GI/MS conduits from one point to another point though separate earthing cable is conncted from DB to Socket?