For testing 33kv cable hipot testing. How much kv we have to
Apply .Give in details.
Answer Posted / bapi
AS HI POT TEST IS CONDUCTED IN DC SO APPROX. 1.5 TIMES OF
AC SUPPLY VOLTAGE IS APPLIED FOR 1 MINUTE.
FOR 33 kV CABLE APPROX. 50kV FOR 1 MINUTE WILL BE APPLIED.
FOR TESTING OF "R" PHASE WE HAVE TO SHORT "Y" AND "B" PHASE
ALONG WITH ARMOUR & IT SHOULD BE EARTHED. SIMILARLY FOR Y &
B PHASE.
AFTER EACH PHASE TESTING IT SHOULD BE DISCHARGED THROUGH
DISCHARGE RODS.
| Is This Answer Correct ? | 66 Yes | 30 No |
Post New Answer View All Answers
why servomotor motor? where i apply for best output?
how can tell us the AC indoor or outdoor which Tr and formulls
What are conduct on the testing in cf in ur site?
WHY NUTRAL GROUND SYSTEM USED IN 33KV SYSTEM
What should be the amps for a MV fuses for transformer 630kVA 20(10)/0.4 kV
explain single phase series motor
Differentiate between ideal and non-ideal voltage sources?
can any one suggest me the tilt angle of my solar pannel ?? or tell me how can i know the fix tilt angle of my solar pannel?? my cordinates are 31.503629,72.993164.
Why does the radius of armature is less than the radius of pole shoe?
what things to be considered when designing UPS
Why the efficiency of a three-phase induction is the motor is less than that of a three-phase transformer?
How to select the gauge of wire for winding of motors? How to select number of turns for winding of three phase induction motor?
full form of electrical?
what will happen if there is a voltage leakage or current leakage in an electrical train
We normally make oil soak pits under Transformers. Oil from soak pit goes to collection pit. We provide granules/pebbles under transformers. My question is weather granules/ pebbles to be filled in soak pit or not? if yes upto what level?