For testing 33kv cable hipot testing. How much kv we have to
Apply .Give in details.
Answer Posted / bapi
AS HI POT TEST IS CONDUCTED IN DC SO APPROX. 1.5 TIMES OF
AC SUPPLY VOLTAGE IS APPLIED FOR 1 MINUTE.
FOR 33 kV CABLE APPROX. 50kV FOR 1 MINUTE WILL BE APPLIED.
FOR TESTING OF "R" PHASE WE HAVE TO SHORT "Y" AND "B" PHASE
ALONG WITH ARMOUR & IT SHOULD BE EARTHED. SIMILARLY FOR Y &
B PHASE.
AFTER EACH PHASE TESTING IT SHOULD BE DISCHARGED THROUGH
DISCHARGE RODS.
Is This Answer Correct ? | 65 Yes | 30 No |
Post New Answer View All Answers
for a 400kv t/m line with 10 ampere current will corona occur?
How to calculate no of EARTH PIT? Describe the formula as per IS standard?
what is the cause of voltage dipp or swell in the transmission lines?
what are factors comes under relay setting (distance relay 7sa52) under OPEN DELTA VTs connection??
What are the three types of compensators?
what is the meaning of osr in transformer.
In between UPS out going changer over switch and ups raising main input, both side cable gland producing heat but the cable doesn't get heat,Why?
What are marginally stable systems?
what is vA rating and class of a ct.
R=*ΒΆ l/a
describe the phenomena of vacuum interruption in C.B
What are the advantages of stationary armature and rotating field system?
what is auto re-closer?
What are the various types of BUSBAR Schemes? explain each
whati s the sludge current in ups