How to find quantity of cement mortar?
I want to know the req quantity of cement for plastering 300
sft in final coat with 12 mm. Any math involved? Plz help
Answer Posted / vkadian
6 bags
300*12=3600/50=72/12=6
| Is This Answer Correct ? | 10 Yes | 33 No |
Post New Answer View All Answers
Did any of the egyptian pyramids ever fall down?
02. a. The diagonal of a 9 cube…………… 1 b. Surface area of 9 cube…………… 1 c. Volume of 1-3 cube …………… 1 d. Compressive area of 6 cube …………… 1 e. Top & Bottom face of a Cylinder/Cube is to be proper leveled to deliver the…………………………..…… properly.
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
how to calculate mivan shuttering matrial
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
If 40 backlogs are cleared m finally with 65 percent marks . Am I eligible to get visa to US
How to activate isometric axes in cad?
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
What Reinforcements Are Used In The Process Of Prestressing?
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing
The concrete slump recommended for beams and slabs; is?
What happens to Load at yielding ?
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??
how much cement and sand consuptin in 4 inch siporex walls 100 sq ft
WHAT THREE SPECFIC JOB POSITIONS TO YOU TARGET FROM THE COMPANY?