As an engineer, what u should do when the construction of a
building doesn't meet the required specifications?
Answer Posted / rqn
if you are with the inspection team, the proper way is to
deduct the cost of the item involve based on the gravity of
damage, however, you have also to consider on the effect of
the item involve with respect to the time element in
completing the project and the structural stability.
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What glue is least sticky?
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
Define What is made from large rocks, which protects the base of cliffs?
Slab quantity
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
What is the best type of wood glue?
strength of bitumen concrete with 80-100 & 60-70 grade bitumen
HOw much % of premium on DSR-2013 currently
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
Can you pl explain the procedure steps of singly and doubly reinforced beams in limit state method
How to come 1.54 from dry to wet concrete?
is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?
For what building Built-on balconies are preferable? What are the advantages?
how much need sand and cement for 1 cft roof construction?