THE 40 MW OF POWER FOR 220 V III PHASE POWER CONNECTION
REQUIRES HOW MANY KVA POWEER REQUIREMENTS

Answer Posted / riyadh

this formula u going to apply

Kw=Kva*P.f

we know P.f = 0.9 for T/f's
P.f = 0.8 for Generator

we knw power kw 40Mw

Apply to above formula Kva = kw / p.f
Kva = 40000 Kw / 0.8
Kva = 50000 kva
In Mva is 50

Is This Answer Correct ?    8 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Is a contactor (or master relay) required between incoming lines and a VFD? The question goes to safety. If a contactor were used before the VFD and an e-stop engaged then the motor will coast to a stop (i.e. VFD loses power) instead of stopping much faster if the VFD braking fucntion were used. It would make more sense to keep power on the VFD.

1549


defult setting in p220 micom motor proction relay for 11kv,640kw,f.l.a.-40a,1440rpm ht motor?

3210


What is the difference between single point and double point bonding. please kindly detail about bonding of cables.

1913


What is nyquist contour?

752


why starting current is high and resistance is almost 0 during the starting of motor dc motor...?

1277






Can you explain about TEE protection scheme?

1748


can you please send me the technical questions and aptitude questions of honeywell and jindal steel electrical engg. question paper my e-mail ID is(kkesavanraj@gmail.com)

1534


Discuss about gear cutting machines.

774


Draw a SLD of HT distribution EB grid up to users Transformer?

5648


what is the efficiency of thyristor

1116


In control room of our one plant there is a continuously the incoming power goes to PC is vary,means in stabilizer it continuously indicate from high input to low and low input to high. what is the reason and its solution.

1489


What will happen if i used 11KV earth ht kit to 11 KV / 11 KV cable termination?

979


Load transfer in 11kv double busbar switchgear - operation.

1490


What will happen if the d.c. Machine is operated below rated speed?

679


Is it required to lay GI wires along with GI/MS conduits from one point to another point though separate earthing cable is conncted from DB to Socket?

1522