If I need to maintain a PP module in SAP from the
information received from another system, Can i use a table
to create the data required for creating the PP
Answer Posted / mpazos1
It depends ¡¡¡
If you only wants to recover some specific data to create
very easy reports, with a few tables it`s enough. This is
the idea as BW works using Infocubes ¡¡¡
But, if you want to get all improvements you can obtain
with PP Module (capacity requrements, MRP evaluation, ...),
so it's stupid to reinvent the wheel: Use this module ¡¡¡
| Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
What is MRP group?
Consignment matl how will be use
What is mrp controller means?
What is 'capacity planning'?
What is costing? How it is affected the pp?
What do you mean by pooled capacity?
What is meant by payscale structure? How did you configure payscale structure?
What is Backflush, the places where the backflush is used?
Integration between PP and MM Module.
Can we use the same routine for materials undergoing the same process/operations? Can we avoid separate routing for each and every material produced?
Define mrp controller
How system calculate the actual cost?
What is a ‘routing’ in pp?
Define mrp list
If there are some errors in goods movements, and less stock of material consumed, how can we solve that problem in sap ?