What will you do, if your subordinate has a problem with
you? How will you deal with this situation

Answer Posted / surender yadav

I would have a patient listening with him. Since project
activities are similar to compartments. Hence frustrations
and anxiety shall be a routine attribute to these
individual compartments. It would be better to explain him
the entire project and his position in the Chain. After all
each of weak chain has to be identified and strenghtened.
The symptons of weak chain may be frustations, blame game
etc. So this would help.

Having a regular meeting with project team helps to ease out
and smoothen the functioning.

However seldom 360 reporting is required and the
subordinate has the right to approach the management.

Is This Answer Correct ?    1 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

During your project meeting, a problem was discussed and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received and e-mail from one of the meeting members saying they've changed their mind about the solution reached in the meeting and need to resurface the problem. The solution reached during the initial project meeting is an example of which of the following conflict resolution techniques? A. Confrontation B. Forcing C. Smoothing D. Storming

551


You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You have been invited to dinner with the prospective foreign business partners and their spouses upon your arrival. You know that all of the following are generally true except: A. You should spend time building relationships with your prospective foreign business partners before getting down to business. B. You should explain your company's rules, standards, and operating policies at your first meeting with the prospective foreign business partners. C. You should build an atmosphere of mutual trust and cooperation. D. You should respect the cultural differences you'll encounter when working with your prospective foreign business partners.

609


How do you handle conflicts in the Team Management ?

545


What are the outputs of the Team Development process? A. Performance improvements, input to performance appraisals B. Input to performance appraisals, reward and recognition systems C. Performance improvements, input to performance appraisals, performance reports D. Work results, input to performance appraisals, performance reports

549


You are a project manager for Waterways Houseboats, Inc. You have been asked to perform a benefit/cost analysis for two proposed projects. Project A costs $2.4 million with potential benefits of $12 million and future operating cost of $3 million. Project B costs $2.8 million with potential benefits of $14 million and future operating costs of $2 million. Which project should you recommend? A. Project A because the cost to implement is cheaper than Project B B. Project A because the potential benefits plus the future operating costs are less in value than the same calculation for Project B C. Project B because the potential benefits minus the implementation and future operating costs are greater in value than the same calculation for Project A D. Project B because the potential benefits minus the costs to implement are greater in value than the same calculation for Project A

666






You are the project manager for Changing Tides video games. You have produced a project network diagram and have updated the activity list. Which process have you just finished? A. The Activity Sequencing process, which identifies all the specific activities of the project B. The Activity Sequencing process, which identifies all the activity dependencies C. The Activity Duration Estimating process, which diagrams project network time estimates D. The Activity Duration Estimating process, which identifies all the dependent activities of the project

504


You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. You are in charge of the network operations part of this project. An important deadline is approaching that depends on the successful completion of the testing phase. You've detected some problems with your hardware in the testing phase and discover that the hardware is not compatible with other network equipment. You take corrective action and exchange the hardware for more compatible equipment. Which of the following is true? A. This is not a corrective action involves human resources, not project resources. B. Corrective action is taken here to make sure the future project outcomes are aligned with the project plan. C. Corrective action is not necessary in this case as the future project outcomes aren't affected. D. Corrective action serves as the change request to authorize exchanging the equipment.

531


You have accumulated project information throughout the project and need to distribute some important information you just received. All of the following are part of information distribution methods except; A. Electronic mail B. Videoconferencing C. Electronic databases D. Voice mail

663


You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. The sub project manager in charge of network operations has reported some hardware problems to you. You’re also having some other coordinating and integrating other elements of the project. Which of the following is true? A. You are in the Project Plan Execution process. B. Your project team doesn't appear to have the right skills and knowledge needed to perform this project. C. You are in the Information Distribution process. D. Your project team could benefit from some team-building exercises.

513


All of the following arc tools and techniques of the Project Plan execution process except: A. Project management information system B. Work authorization system C. Organizational policies D. General management skills

526


These diagrams rank order factors for corrective action by frequency of occurrence. They are also a type of histogram: A. Control charts B. Process flowcharts C. Scatter diagrams D. Pareto diagrams

713


All of the following are true regarding the ADM method except: A. It's a tool and technique of Activity Sequencing. B. It uses one time estimate to determine durations. C. It's also called AOA. D. It's rarely used today.

667


You have been asked to submit a proposal for a project that has been put out for bid. Prior to submitting the proposal, your company must register so that their firm is on the qualified seller list. Which of the following is true? A. The qualified seller list provides information about the sellers and is a tool and technique of the Solicitation process. B. The qualified seller list provides information about the project and the company that wrote the RFP and is an input to the Solicitation process. C. The qualified seller list provides information about the project and the company that wrote the RFP and is a tool and technique of the Source Selection process. D. The qualified seller list provides information about the sellers and is an input to the Solicitation process.

520


Your project has recently experienced change. Some of the agreed-upon WBS elements have been changed as a result. What kind of change has occurred? A. Schedule change B. Risk response change C. Quality change D. Scope change

624


Describe function-oriented metrics.

502