Answer Posted / rama koteswara rao
BTC (background):
- Number of processes: at least 1 in each system, during the
upgrade, at least 2.
- Reservation of processes for job class A:
If n background processes are running, a maximum of n-1
processes may be reserved for class A jobs, as jobs with
class
B and C would otherwise be blocked (see Note 36280).
| Is This Answer Correct ? | 9 Yes | 1 No |
Post New Answer View All Answers
How to update SAP
Which table contains the details related to Q defined in SPAM? Is there a way to revert back the Q defined? If yes, How?
What is Unit Testing in SAP?
suppose in the landscape there is development, quality, pre-production and production system is there. what is the route(transport route) between pre-production to production? and why?
What is ocm and how to apply ocm patches?
Explain what is the use of reference and service user in sap?
Hi ,All What is the multi-threading and max connections for rfc. Actually i am facing problem while send large amount of idocs to external system using middle ware tibco r3 adapter. And how to enable these in SAP ?
Explain deletion flag?
Where do you check transport request logs?
What is a developer key? and how to generate a developer key?
Is it possible to install sap patches when other users are online?
How to identify a particular T_Code has been modified or not? If yes, how to identify who modified particular T_Code in current system?
What are the regular activities u do in solution manager and how
Do you know about oss what do you do with oss?
What is the use of patches in sap system? Could you name few common patch types?