Do you know the faults occurs generally in motors and how
to rectify them?
Answer Posted / kannan
1. Over load tripping - Reset OL relay.
2. Ball bearing failure - To be identify by heavy noice and
offton tripping & Over heat - Change bearing.
3.Monthly once clean the body of the motor. cooling will be
better.
4. Winding problem. - Check by megger of multi meter.
Rewinding to be done.
5. Over load relay itself problem some times.
| Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
How impulse levels are calculated that for 11kV impulse is 75kvp, for 24kV impulse is 125kvp ?
I am experienced with house and industrial wiring but I don't have any licence how can I apply an licence and which type of licence i can get i didn't complete deee just only experience
What are the factors which influence the choice of specific magnetic and electric loadings of a synchronous machine?
can i use the six sigma method which is used in management area, in state estimation of power systems?
Why Transformer Neutral having one earth pit ( more earth electrode resistance) whereas body have many earth pit ( less earth electrode resistance)?
What is the safety of UPS?
While performing stability test of differintial cts how to know the voltage and current on both side of the transformer?
in wind mill use 2100 kw asychronous generator ( induction generator ) rotor voltage : 3300,stator voltage : 690, rpm : 1511 type : MRL063E04 ' we check rotor resistance magger value found following. R-EARTH - 00 M.OHM,Y-EARTH-34 M.OHM,B-EARTH- 33M.OHM R-Y: 31 M.OHM, Y-B: 00 M.OHM,B-R :33 M.OHM HOW CAN I TAKE DECISION?pls ans. quickly
On what basis do you decide the ONAN (Oil Natural air natural) or Dry type transformer for a project?
what is thermal resistance of PVC Cable.
Is better to supply the voltage for static exciter from the auxiliary power source or from the SG terminals? And why?
what is the purpose of bypass mode in energy lighting transformer?
what will be project cost for 100 kv transformer connection under oyt scheme.
for a 400kv t/m line with 10 ampere current will corona occur?