Answer Posted / ramya
combinality is a mode in Advance tab of a stage.
The mode can have values: Auto, Combinable, Don't Combine.
Auto: let the DataStage decide whether to combine the
stages
Combinable: Combine the operator with other stage if
possible
Don't Combine: do not combine them at all
I think Don't Combine may be non combinability in your
terms.
| Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
A signal has a wavelength of 1 micro min in air.how far can the front of the wave travel during 1000periods?
On which interface you will be working as a developer?
In Datastage, how you can fix the truncated data error?
How many Key we can define in remove duplicate stage?
Differentiate between datastage and informatica?
If you want to use a same piece of code in different jobs, how will you achieve this?
In a batch if a job fails in between and you want to restart the batch from that particular job and not from the scratch then what will you do?
How to Remove Duplicate using SQL?
Which algorithm you used for your hashfile?
Can you explain how could anyone drop the index before loading the data in target in datastage?
project Steps,hits, Project level HArd things,Solved methods?
Different ways a project can be moved to production ?...example ….export-import and Version control.
i have a job with 3 possibiliies finish with ststus ok abbort warning how do you handle these 3 in job sequence? explain the situation where you have appiled scd in your project? chandu
how can we validate the flat files using the date in the header and number of records in the flat file? Using both conditions at a time.
Differentiate between hash file and sequential file?