Answer Posted / jinu
the major difference in between sap r/3 and APO is that in
sap r/3 excecuting of production orders or purchase
orders,material withdrawal and costing takesplace,whereas
in apo only planning can be performed,
Sales orders are only created in SAP R/3 whereas in APO it
is not created.
IN APO planning is done for the critical materials using
MRP type X0.
Is This Answer Correct ? | 20 Yes | 1 No |
Post New Answer View All Answers
Define mrp group
What is MRP Area or How can I excluede one storage location stock from MRP?
What are the production process in sap?
Explain why there is need of production version?
What is the output of mps run ?
What is time phased Planning?
What are the types of master views for production and planning?
Explain LTP.
What is opening period?
What are the t-codes for creating, changing and summarizing bom?
What are the different type of BOM usage?
What is the internal recruitment?
Why work scheduling view is required for semi-finished and finished products?
One component we can assign to workcenter at routing
Mention how mrp (material requirement planning) types are classified?