1KVA transformer of different frequencies of
50hz,100hz,500hz&1000hz. which one of these transformer has
big size? Give reason
Answer Posted / kishore
X(1 KVA) 50 HZ n Y(1 KVA ) 500 HZ
E = 4.44 f * FLUX * N
that is emf durectly proportional to flux which is f*B*A
B- flux density n A= area of c/s of transformer
as KVA reting of both are same n hence
X (f*B*A) = Y (f*B*A)
as frequency of X is smaller than Y so area of c/s of X
must be larger
hence 50 HZ transformer is largest and so on
kishoresahoo@ymail.com
| Is This Answer Correct ? | 39 Yes | 8 No |
Post New Answer View All Answers
What is meant by time harmonics and space harmonics?
What are the functions of different probes used in cro?
What is making & breaking current ???
WHAT IS MEANT BY SHEATH VOLTAGE IN 132Kv cable?
What is step signal?
what is the voltage rating of chiller unit sensors
In the magnetic fluxes, what is the role of armature reaction?
why we dont prefer ac voltage controller instead dimmerstat [if both have same rating] for conducting experiments in laboratories?
Show Details FROM:Muhammed Ikram TO:qa@allinterview.com Message flagged Saturday, June 4, 2011 10:07 PMMessage bodyHello all, i want to ask a question to all of you that what is VMM (voltage monitoring module )? how it work,s? i heard somewhere that it compare 1 phase voltage to other phase voltage. but there is also some setting on it. how to set it,s setting. please tell me briefly. Thank,s and Regard,s. Muhammed Ikram.
While converting delta into star or star into delta ,the three values of resistances remains unchanged .Find out the value?Let In star R1=x;r2=x;R3=x On converting into delta,R12=x;R23=x;R31=x Find the value of x
what is the difference between STAR and DELTA connection and application wise how it can be utilizedd
can we synchronize star system generators with delta system transmission line ? and how ?
what are the tests comes under the type test, what tests comes under routine tests.
How to calculate cable size in HT AND LT
why various test are performed on electrical panels & power cables before commissioning on site & what are these test???