Answer Posted / devesh bohre
we can take is as"where used Item" by which one can come to
know about the presenece of one particular Item
(RM/SF/Componant) in Numbers of Finished good or in various
BOMs.
e.g
if item A is used in BOM of S,T U and X and X is also used
in S so out put will be as
A--S--x
--T
--U
--X
| Is This Answer Correct ? | 5 Yes | 2 No |
Post New Answer View All Answers
What happens to plan after it has been converted into production order?
Explain what is the meaning of exploding a bom?
Where we have to specify the teardown time in one operation?
Define 'sop' (sales & operations planning)?
How requirements( pir,sles order, customer requirement) are reduced after they are produced?
Explain DMR.
Difference between Item categories or what is variable size item or non stock item.
We want the system to run a single level mrp automatically on receipt of the sales order. How to configure triggering event based mrp?
Explain Flexible planning Procedure?
What is meaning of customized reports?
What is Material status and which view of the material master it is available?
How do you do capacity planning ?
What is process keys
How costing is affected the pp?
Splitting of production order & product version